Can I build an ADU on my lot?
Almost certainly. California law allows at least one ADU and one junior ADU on most single-family lots, and the City of San Diego generally follows these state rules. Multifamily properties can add ADUs too, often by converting unused space like storage rooms or garages.
- Detached ADUs can typically be up to 1,200 sq ft.
- Height: 16 ft is allowed in most cases, and more near transit or for two-story designs that meet certain conditions.
- Parking: often not required, especially within half a mile of transit or when converting a garage.
- Owner occupancy: not required for ADUs, so you can rent both units.
What does an ADU cost in San Diego?
Typical all-in costs in the City of San Diego, including design, permits and construction:
| ADU type | Typical size | Typical cost |
|---|---|---|
| Detached ADU | 500 to 1,200 sq ft | $200k to $450k+ |
| Attached ADU | 400 to 1,000 sq ft | $180k to $400k |
| Garage conversion | 300 to 500 sq ft | $60k to $150k |
| Junior ADU | Up to 500 sq ft | $40k to $100k |
Use the calculator for an estimate based on your size, finishes and lot.
ADUs around the city, neighborhood by neighborhood
The City of San Diego covers a lot of ground, and the right ADU depends on where you live.
| Neighborhood | What fits best | Things to know |
|---|---|---|
| Clairemont | Detached ADUs | Large, flat mid-century lots with easy backyard access |
| North Park, Normal Heights, City Heights | Garage conversions, detached ADUs | Older homes, detached garages and alleys; check for historic district rules on some blocks |
| Point Loma, La Jolla | Detached ADUs | Hillside lots and higher finish costs; parts are in the Coastal Zone, which can add a permit step |
| Mira Mesa, Rancho Bernardo, Scripps Ranch | Junior ADUs, attached ADUs | Newer tract homes; check HOA design guidelines, which can't ban ADUs but can affect looks |
| Pacific Beach, Ocean Beach | Garage conversions, compact ADUs | Small lots, strong rental demand, and Coastal Zone rules on many blocks |
| Encanto, Paradise Hills | Detached ADUs | Bigger lots, some slopes; good value for rental units |
The permit process, step by step
- Feasibility (1 to 2 weeks). Check zoning, setbacks, utilities and any easements on your lot.
- Design and plans (4 to 10 weeks). Your builder or designer prepares architectural, structural and Title 24 energy plans.
- Plan check (6 to 12 weeks). Submit through the city's online permit portal. Expect at least one round of corrections.
- Permit issued. Pay remaining fees and schedule construction.
- Construction (5 to 9 months). City inspections happen at each major stage.
- Final inspection. Once approved, your ADU is ready to live in or rent.
How much rent can a San Diego ADU earn?
Rents vary by neighborhood, but typical ranges are about $1,800 to $2,300 a month for a studio, $2,200 to $2,850 for one bedroom, and $2,800 to $3,500 for two bedrooms. Coastal neighborhoods like Pacific Beach and La Jolla are often higher.
Frequently asked questions
How long does an ADU permit take in San Diego?
Once your application is complete, state law requires the city to act within 60 days. In practice, the full plan check process, including corrections, often takes 2 to 4 months.
Can I build two ADUs?
On most single-family lots you can build one ADU plus one junior ADU. Some properties may qualify for more under city programs, which have changed recently, so check current rules.
Can I sell my ADU separately?
New state law (AB 1033) lets cities allow ADUs to be sold separately as condominiums. Ask the city whether it has adopted this option before planning around it.